Friday 13 December 2019

Digging and more Digging! Boat of Garten - 11th December 2019

Mid week produced a welcome massive squad of eight, Georgie tasked Angus and I to obtain and put up the Temporary Speed Restriction (TSR) Boards required for the proposed switch into Boat of Garten North Yard,
 
 
unfortunately we could not source a 10 mph board for the above Warning Board but sharp eyed Drivers should be able to spot the 10 at the Commencement Board though!
Plumber Jim was mildly critical of their plumbness, I retorted that they lean into the prevailing wind so that they don't blow over! 
 
 
 Once we had finished that Angus and I joined the main squad, in a continuation from last Saturday, of digging out the ballast to the bottom of the sleepers.
 
 
Admiring job done, right up to the North end of the Boat of Garten bridge, in the background at the 88 3/4 mile post can be seen the Termination Board of the speed restriction and on the obverse is the 10 mph Commencement Board for Up trains heading towards Aviemore.   
 
 
As we had daylight still available Georgie told us to remove the excess ballast from the four foot (between rails) and build up the shoulders further down the line. The photos do not do the inclement weather justice as there was a biting wind and snow showers (my camera does not like any form of precipitation) but many thanks to Graeme, Martin, Andrew, Fergus, Mike, Angus and Jim for braving the elements and the hard labour.


No comments:

Post a Comment