Saturday, 8 February 2025

Broomhill plain lined - Week ending 8th February 2025

Mike reports with below photos - Wednesday 5th saw a small squad meet Broomhill


another 16 sleepers pre-drilled and PAN11 baseplates fitted, last of timbers removed using Colmar and Fergus in JCB.


Ballast cleared out, hopefully to the correct level, using GPS (a.k.a. Georgie) controlled JCB & the high-tech laser sighting boards !
--------------------------------------------------------------


Scene at start of a chilly Saturday 8th Feb


and by mid afternoon!


Fergus further reports with above photo - Rails dropped in, fishplated and outside pandrols hammered in! (Pan puller missing) fun was had with the closure rails......

Thanks to Mike, Fergus, David, Andrew & Michael showed up after lunch 










 