Sunday 7 September 2014

Extension Work 6&7th September 2014

 

Ironing out the hollows continued this weekend using the very useful Jacker Packer, I believe that spares, sourced by Ian from South Tynedale Railway at Alston, have now been paid for and only the logistics of getting them up here are now in hand.
 
 
Mike & Ian survey their work, continuing the clearing by hand of the Down Cess from the "BG" to the Dulnain bridge, as it is likely to be used a lot, walking back and forth for tools and of course, the odd Tea Break!