Sunday 15 September 2024

Road two taking shape - 13th & 14th September 2024

On Friday 13th! Ian reports -



"Iain Ross and self were taxed with drilling the rest of the softwood sleepers, and putting 1 chair on them; the other end of most of them will have a check chair and therefore the spacing is different. We also plugged and drilled 4 hardwood timbers which are sat towards the pit, and chairs were added both ends to them. Georgie was busy infilling the ductwork trench, after laying in witness tape to permit future maintenance staff to be aware of the route of the duct"

--------------------------------

Saturday saw a bigger squad of  Mike, David, Richard and Iain again


Above a new method of joining timbers at switch levers.


As can be seen above both switches in and fixed down, sleepers laid out to take closure rails, chairs have ferrules. Georgie seemed pleased with progress.
Thanks to all that attended and Ian & Mike for respective reports and photos. 





 

Tuesday 10 September 2024

Rare future proofing at Aviemore - 10th Sept 2024

An extra mid-week day saw unexpected progress


Georgie had marked out all the sleepers that required drilling using the bullhead jig, I drilled and Roddy screwed down the pre-prepared chairs - back breaking stuff and no shorts worn today as about 20 degrees Celsius less than Saturday! with cooling blustery heavy rain, after lunch Georgie asked if we wanted a change in tasking?


Whilst Georgie dug the trench we carried the ducting some 200 yards to site, not so easy with the gusty winds.


Rope tied to fishplate and launched through each length, then all joined together and partially buried by hand, a water pipe was also buried - all in the name of future proofing - a rare concept at the Strathspey Railway I know but certainly easier than trying to burrow under the track as the S&T recently found out.
Thanks to Roddy and Georgie whom we left filling in using the JCB.   



 

 
 

Sunday 8 September 2024

Components getting in place Aviemore - 7th Sept 2024

Squad met at Aviemore and divided up - Roddy and myself tasked with oiling all the switch slidechairs at Aviemore, others sent to the Headshunt to finish packing and tidying from last Month, others putting ferrels in all the AS1 chairs to be found


By the time our respective tasks completed, Georgie had shunted vehicles out the way and a start was made 


laying component parts in approximate situ 


One switch rail and the crossing in the distance


By the end of the day we were all puggled by the heat, possibly Newton's third law in operation above!
Thanks to Roddy for the larger photos
Thanks to Michael, Ian, Fergus, David, Martin, Roddy and Georgie, a few of us attended an end of main season very enjoyable soiree at Aviemore Station, paid for by the Strathspey Railway Company.





 

Monday 19 August 2024

Aviemore Works - Week ending 17th August 2024

Tuesday I think - Fergus made a start on the refurbishment 


of the stonework in pit, road two at Aviemore Shed.


Spoil wagons at the ready, site still to be levelled in the foreground, with another PWay train (ballast) arriving in the background. Thanks to Ryan for the above photos on Wednesday.
-----------------------------

By Saturday this was the start of work (or so we thought!)


site cleared through the week by Georgie and


concrete sleepers, switch & crossing, timbers and wooden sleepers all at the ready.


Alas we were diverted to the North Headshunt at Aviemore for more urgent repairs.
Thanks to John, Mike, David and Richard & Ian were part timers this time. 













 

Sunday 11 August 2024

New Works Aviemore, Broohmill nearly concluded - 7&10th August 2024

Unexpectedly Wednesday's midweek squad was summoned to rendezvous Aviemore Shed, 


for sometime road two pit has been out of use awaiting refurbishment.


Georgie has taken the opportunity to also reconnect road one at the same time, apparently Shed Staff require it all to be done within three Months.... Roddy above makes a back breaking start removing all the fishplates towards shed doors, Mike failed to find the appropriate socket for powertool assistance!


Georgie more successful with attachments for Road Rail Vehicle.   


All rails, spoil and timbers large and small removed onto PWay trains, which were shunted about the yard by Nathan. Still a lot of manual lifting required, the very old chairs are heavier than they look and safely stacked away for future use.
Thanks to Mike, Roddy, David.
-------------------------------------------

Saturday saw squad back at Broomhill almost concluding works there. 


Thanks to Mike (who was sent on a Track Inspection) Richard, David, Fergus and Michael (part-timer!)









 

Sunday 7 July 2024

Broomhill Up Cess - 6th July 2024


 Its been a while and we are still at Broomhill re-sleepering and inserting Pan 11 baseplates - more in a future blog.

 

Yesterday saw a small squad of only two - David and myself tidy the ballast in the four foot where the re-sleepering is completed on the mainline in the distance.  


By the time Georgie arrived we were onto trying to recreate the Up Cess, 


which was ideal as no one can finish it off better than her!

POLITE NOTICE from her to Enginecrew and others Please Do Not disturb the ballast on the shoulder!






Sunday 21 April 2024

Broomhill S&C complete? - 20th April 2024


It has been a while since the last post, holidays etc. - Mike reports
Saturday 20th April saw a good squad meet up yet again at Broomhill, the order of the day was many track jacks and much jacking and packing of the newly installed switch and crossing (S&C) at the North end of the run-round loop, followed by Georgie's requisite
 "now tidy up the ballast boys"!   


By the time Mike took the above photos, David (been away - injury and a wee trip to New Zealand) and himself had been tasked to oil all the S&C fishplates 


and tighten to the correct torque, whilst the rest of the squad joined by Fergus after his Aviemore Section Track Inspection had started the tiring digging out the sleepers in the loop that require changing............next time.

Thanks to - Georgie, Mike, David, Richard, Steve (new chap) Ian and Iain.