Another weekend of the week long cold snap and more snow, meant P'Way had other duties
An attempt to document the activities of the Strathspey Railway permanent way department
Saturday 17 December 2022
Boat of Garten Water Tower - 17th December 2022
Saturday 10 December 2022
Festive white stuff cancels P'Way work - 10th December 2022
Wednesday 7 December 2022
Another Friday Packing - 2nd December 2022
Saturday 26 November 2022
Kinchurdy Down Distant to Level Crossing - 25/26th November 2022
Thanks to all mentioned.
------------------------------
The following day -Saturday 26th saw the commencement of the festive train service and the P'Way having given up their Absolute Possession of the Line the day before,
with the Temporary Speed Restriction (TSR) Notices posted at the appropriate locations
and the refectorised on track reminder boards in situ, the first of the Express trains eventually passed us at a sedate steamy 10 miles per hour.
The mammoth task of re-sleepering started in ernest today. As Georgie expected, a certain amount of re-gauging was required, only the high rail sleepers had been pre-drilled, the opportunity was also taken to replace all of the remaining wooden ferrules/ & worn screws with new. Both Mike & I were glad Fergus was with us as he seems to be able to throw the heavy sleepers about with ease. Approximately 20 sleepers changed in just over two lengths, took us beyond Kinchurdy Level Crossing but a long way to go.......
Thanks to all that attended and the warm sunny weather!
Friday 25 November 2022
Dalfaber Level Crossing and Jacker Packer - 19th November 2022
Monday 14 November 2022
More Sleeper pre-drilling - Saturday 12th November 2022
Thursday 27 October 2022
Progress on three fronts - 27th October 2022
Saturday 22nd October not a P'Way day, the opportunity was taken to rediscover the old platelayers cottages from the encroaching vegetation at Broomhill.
Before
Saturday 15 October 2022
Recent On & Off Track progress - Week Ending 15th October 2022
Off Track to start, the Signalbox at Aviemore is receiving a much needed external refurbishment and repaint more detailed (accurate) accounts can be found on https://signallingstrathspey.blogspot.com/
What won't be found is a photo of the stalwart main volunteers that have of recent years refurbished/painted Boat of Garten :- Signalbox, Station & North Cabin and many other projects - on the left (keeping warm and maybe giving orders!) Colin Frost and Ray Kenyon (multi tasking doing a bit of re-glazing). The Strathspey Railway Directors have promised them a lunch on the train as an expression of their gratitude. Colin has thanked his friends from Ellon and the small part that the P'way squad managed to contribute.
Saturday 8 October 2022
Civil Engineers Fleet expands - September & early October 2022
Sunday 28 August 2022
Boat of Garten North worksite concludes - 20th - 27th August 2022
Gang met up again at Morley's on the last formal P'Way weekend of the Month 20th August
Re-sleepering continued and has now concluded for the time being, above shows a bonded joint to assist with the continuity of S&T track circuits (not many were harmed!).
Station Master or Royal Scotsman or Ballast Guard - R Walters report and photos 24th August "As soon as the last service of the day, hauled by the Class 2
Ivatt, has entered the single line to Aviemore, a ballast train sneaks
out of the Up Loop, hauled by the Class 27 Diesel, whilst Royal
Scotsman, complete with its own liveried Class 66 locomotive trailing
behind our Class 31 awaits its guests before setting off for Dundee.
The ballast train loaded with spoil from the new Running Shed excavations proceeding past Royal Scotsman towards Broomhill, with newly renovated LMS Brake Van at the rear."
--------------------------------------
Yesterday saw an extra P'Way day squeezed in, Mike and Georgie were very glad to see Bruce who is up from Wiltshire (below foreground)
Thanks to all, especially Bruce, thus enabling squad to move onto another worksite next time.
Monday 15 August 2022
Boat Trackwork - 6th & 13th August 2022
Mike Tough belatedly reports for Saturday 6th August - "worksite Mile post 90 1/2
Rail regulation after reports of a noisy joint ( did not say broken fishplates ) caused by cooler weather after hot spell
7 joints 6 rails had to be freed off the dreaded elastic spikes first
Then joint and other measured shovel packing."
With thanks to Georgie, Ian, Kevin Morris, Andrew, Mike Tough and especially Baptiste as it was his last P'Way day before he heads back home to Lyon, photos below from resident Station Master Walters,
We envied the farmer in his nice air conditioned cab! It was so hot that we had luncheon inside the P'Way lant Maintenance Shed aka Morley's (mark 2) and Georgie even treated us to ice creams (some had more than one! - Michael)
Here the guage was found to be slightly tight, necessitating removal of screws 2 chairs either side and then applying back to back track jacks to maintain the correct distance whilst drilling, rior to screwing down.