Sunday, 16 March 2025

An extra day squeezed in completes two projects - 14/15 March 2025

An extra PWay day was arranged for Friday and thankfully a big squad responded.
 

Location - Broomhill Loop, task - install Trap Switch.
Beds dug out, fishplates removed and not least the notoriously difficult to remove elastic spikes (thanks to Fergus) 


Sleepers/rail removed (by machine) bed lowered by an inch


to accommodate thicker timbers, some of the squad were detailed to retrieve all scrap materials from the North end of Loop. 


Meanwhile Mike and Ian (above) filled with concrete, their previously constructed shuttering on the four legs of the watertower at Boat of Garten.

----------------------

Saturday saw a smaller squad continue in warmer weather


Above John on rail drill and Andrew exercising!




The finished product, fishplate securing it Out Of Use, until such time as through running achieved beyond Broomhill and it would effectively become a siding (S&T would need to connect it all up and obviously move the Stop board!) 

Thanks to Mike, Michael, Roddy, Angus, Martin, John, Andrew, Iain and special mention to Fergus, Ian and myself who survived two consecutive days under Georgie's leadership.












 

Monday, 10 March 2025

Broomhill plainline complete - Saturday 8th March

Saturday saw a Broomhill meet, the February service trains compacted the hand packed ballast sufficiently to allow for Measured Shovel Packing to commence - 


although there were some big lifts and many chippies consumed, above photo shows Gang just prior to slewing 

and after much huffing, puffing and walking up and down, Georgie was satisfied with the result.
 Thanks to Fergus, Angus, Michael & Mike and Ian who provided photos/info.