Sunday, 28 February 2016

Plumbing in Water Crane at Boat of Garten - 27th February 2016

Jim Clark made a welcome return after his health wobble late last year, everyone was pleased to see him and of course his plumbing skills were soon put to good use.
 
 
Above shows close up of the 6 inch valve furthest away in blue and connections to the plastic piping.
 
 
Maybe a way of merging these photos but beyond me!
Anyway Jim does the honours in opening the value with Stuart looking on nervously!
 
 
I think there was shuttering mentioned to pour in concrete, encasing the metal parts?  
Thanks to John Wood for the photos and information.  
 
 
 
 


Monday, 22 February 2016

Jacker Packer Aviemore Loop - 21st Febuary 2016


The Jacker Packer has been stored on it's stand by the turntable at Aviemore for some weeks now, poised for action and once the Diesel Multiple Unit had departed Aviemore Station Limits, we set about putting it on rail
 
by laying the stand rails on the rails at right angles
 


then Stuart carefully drove forward, below the centre of Packer a hydraulic turntable foot lifts the machine upwards to clear the wheels from the stand rails, then by hand it is rotated 90 degrees and by lining up the wheels, carefully lowered onto the rails, then driven to the worksite which was the Loop line in the Station.
 

Ballast having previously been dropped and ploughed by Georgie had to still be shovelled onto the far away shoulder, so that there was enough to pack under it. Above Angus (who braved the miserable weather two days running) starts this process. 
 

Here Mike guides Stuart on getting the track level. As mentioned the DMU was running, which was a pity as I could have done with more breaks as there was no requirement for it to use the Loop.
 
 
Of course after packing there was the obligatory tidying up of the ballast ,which we did not manage to complete but it sure looks a lot better than it did.




 
   
 
 


Re-Sleepering Tullochgorum - 20th February 2016

I wonder if this was the last sleeper to spike?
 
 
Angus, Andrew, Fergus and John braved the elements to assist Georgie and Stuart in drilling, spiking, packing and boxing in the last of the sleepers, finishing off the major spot re-sleepering exercise since the 4th July 2015 from milepost 89 and 3/4 up to and just beyond the 91 milepost. I don't recall exactly how many were changed but I do know that all concerned are glad that it is finally finished.
 

As can be seen from above the opportunity was also taken to tidy up the formation and cess. Thanks to John Wood for information and photos.
 
 
 
 
 


Saturday, 6 February 2016

Aviemore Timber replacement - 6th February 2016

 
Timber replacement on the switch from the Mainline into the Headshunt at Aviemore required a good turnout and the Volunteers didn't disappoint. 
 

 
Above Martin, Angus and I guess John H (taking photo) dig out pebble ballast of the Mainline
 
 
and Neil H, Ian, John W and Fergus dig out the much lighter Ash of line towards Headshunt.
 
 
Maybe a 15 foot Timber being manpowered into position. 
 
 
 
7ton lifting jacks need strategic placing so that the required section of rails are lifted and the old, very heavy, water sodden timbers can be pulled out and the new ones put in.
 
 
recently retired Angus lifts the Timber whilst Martin packs material under it, prior to drilling.
 
 
I believe much to everyone's delight the task was completed through teamwork and pleasant working weather.
 
To keep the peace I have used photos from John Hornby, John Wood and Keith Holyland, Thank you all.
 



Re-sleepering towards 91 milepost and beyond - 4th February 2016

Small squad of three continued re-sleepering towards 91 milepost, we managed to complete the 14 beds that were dug out, to find two spare sleepers that were put to good use further Down the line. Drilling spiking and boxing-in are the remaining tasks. No further photos of re-sleepering are thought necessary for a while!
 
 
Whilst we were in the area, Georgie got Mike to have a look at a culvert that had previously been spotted, when I think Georgie, John, Angus and Fergus had the unenviable task of clearing ditches and culverts of any debris, from about Fishermans' Crossing.  

 
Difficult to see from the above photo but one of the granite blocks in the water are meant to be supporting the left side of the large heavy lintel, which if left would eventually fall, possibly blocking the culvert. A plan is now in place, once the water levels go down to repair it.

 
Back at Boat of Garten, Georgie has for some time been working on the water tower, giving it an almost complete, new all weather watering facility, as the out of shot, water crane on the Down platform had a tendency to freeze up and as yet it is not yet repaired after a burst. This replaces the temporary measures put in place as seen in November Blog. No doubt the Signalling & Telegraph Department  (S&T) will complain about our two extra stay wires obscuring their yet to be commissioned signal arm but compared to the just visible Stop Board !


Monday, 18 January 2016

Aviemore Engine Shed Concreteing - 17th January 2016

 
 
 
Scene some weeks ago, with plinth locations marked out. (photo from Keith Holyland)




 
 
The shuttering was erected (see earlier Blogs), here John again checks the levels. The reinforcing grid was removed and placed in again half way through the pour of concrete.
 
 
Georgie in action! to stop leakage from round the base of shuttering post-crete was used to seal.
 

 
Here Stuart and Andrew "Supervise" Ian's daughter, as can be seen she worked very hard,  the heater was used to assist in defrosting the sand and possibly keeping Stuarts hands warm!
 
 
Finished product as smoothed by Georgie.

 
Polythene was secured over the shuttering to keep surfaces clean and keep some of the heat in, as it was a mere 2 degrees Celsius.
 
 
Even with Calum here thinking he is firing Flying Scotsman!
(see http://www.thewatkinsontrust.blogspot.co.uk/ for more photos of the heater)
 
   
 
 
Since we had a big squad, eleven in total, some proper PWay maintenance work was also done on the Switches and Crossings (S&C) - loosening off bolts, oiling them and re-tightening.
Left to Right - Bruce, Angus and Andrew
 


 

 

Wednesday, 6 January 2016

Mezzainine Flooring and re-sleepering - 29th December & 3rd January

 
29th of December 2015 - saw the completion of a long running project, (I think Mike mentioned the steel work was erected in 2014) the Mezzanine Flooring in the Aviemore Engine Shed.
Ian Stanworth put in 700ish screws in the actual flooring and John Wood assisted him in putting on the kick boards on the hand rails and boarding off the arches, to prevent anyone or anything falling through them to the Machine Shop below, where Mike and Georgie set up shuttering for concrete plinths, for the "new" machines that are almost in situ... 
 
 
 The above photo reminds me of that television programme "Play School",no reference to the Shed Staff you understand! I wonder how long it will take them to fill it up with stuff.....
 
Later the same week but a different year (3rd January 2016) the PWay back to re-sleepering towards the 91 mile post. Georgie, Mike and John changed an incredible 38 sleepers in freezing wet conditions - only drilling, spiking and backfilling to do.
 
 
The elusive 91 mile post is getting closer, by the looks of things.
Thanks to John Wood for photos and information .