Friday 3rd February saw small squad head out to Kinchurdy with Ian operating the recently repaired Jacker Packer to lift track and pack (as below and repeat many times!) - to facilitate the renewing of sleepers.
Alas sleepers either side of the joints still needed hand packing,
ably done by Mike and Andrew above (who is not rolling a joint, I trust!) anyway the 87 & one half mile post was reached without incident, as asked for by Georgie, who was loading a spoil train at Aviemore.
Thanks to Ian, Andrew and Mike who supplied info/photo/clip.
--------------------
No PWay progress Saturday 4th as a carriage was partly delivered by contractors.